Data Center Directory

Meta Gallatin

Meta Gallatin is an operational AI data center operated by Meta in Gallatin, United States. Its power is about 114 MW. Epoch AI estimates about 100,000 H100-equivalent AI chips (B300).

Key facts

StatusOperational
OperatorMeta
UsersMeta
Facility power114 MW
Reported (Epoch AI or owner data)
IT power87 MW
AI compute100,000 H100-equivalents
AI chipsB300
Reported (Epoch AI or owner data)
GPU capacity if all AIabout 48,000 GPUs
If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count.
Capital costUSD 3.3 billion
Epoch AI estimate, 2025 USD.
Address1 Meta Lp, Gallatin, TN 37066
Coordinates36.38830, -86.44759 (city level)

Build timeline

DatePowerH100eWhat the satellite images and filings show
2023-09-1100Land clearing starts for Building 1.
2026-02-0900Building 1 shell and cooling looks complete, but construction equipment is still seen around cooling and building.
2026-08-24114 MW100,000Building 1 is operational, based on a lack of construction activity around the shell and cooling equipment, and about 6 months passing after structural completion.

Source: Epoch AI Frontier Data Centers.

Chip deployments

DateChipUnitsBasis
2026-08-24B30039,453Estimate

Satellite view

Questions

How much power does Meta Gallatin use?

Public data puts the facility power at about 114 MW. Reported (Epoch AI or owner data).

What chips does Meta Gallatin use?

Reported chips: B300.

Who operates Meta Gallatin?

Meta. Reported users: Meta.

Data centers near Gallatin

More Meta data centers

Sources

Correct this page or get the data

Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.