Meta Prometheus

Meta Prometheus is an operational data center that is still expanding, operated by Meta in New Albany, United States. Its power is about 612 MW, growing to about 1.3 GW by 2028-07. Epoch AI estimates about 536,000 H100-equivalent AI chips (B300).

Power demand is growing at this site

Key facts

StatusOperational, expanding
OperatorMeta
UsersMeta
ProjectPrometheus
Facility power612 MW
Reported (Epoch AI or owner data)
IT power471 MW
Planned power1.3 GW by 2028-07-01
Epoch AI timeline projection.
AI compute536,000 H100-equivalents → 1.2 million planned
AI chipsB300
Reported (Epoch AI or owner data)
GPU capacity if all AIabout 260,000 GPUs
If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count.
Capital costUSD 17.8 billion → 38.7 billion planned
Epoch AI estimate, 2025 USD.
Energy partnersWilliams, American Electric Power
Address1 Community Cir, New Albany, OH 43054
Coordinates40.08117, -82.80879 (city level)

Build timeline

DatePowerH100eWhat the satellite images and filings show
2022-04-1400Land clearing begins for Building 1-2
2025-06-0100Roof complete on Building 5 (QTS-owned). In the northernmost area, land clearing begins on a new Meta site for Buildings 16-20. Building 1 still has construction work around the building and cooling equipment, so it's unlikely to be operational.
2025-09-2000Building 4 operational. Based on our default estimate of roof-to-operational time.
2025-10-1499 MW87,000Building 1 is operational, based on there being minimal construction work and cars in the main carpark. Building 2 still has some construction work around the building. Building 18 roof is complete. The on-site power at Socrates South and Socrates North has some outlines of gas turbines, to be installed later.
2026-01-18478 MW419,000Buildings 2-6 are operational, based on all equipment being in place, the paved ground, and minimal construction equipment by the buildings. Buildings 7-11 all have some kind of power or cooling equipment lining their right side which are not fully installed. Building 14 has chillers installed. Buildings 16-20 roofs are complete. The Socrates South power plant to the right of Buildings 7-11 has 7 gas turbines in place, judging by the exhaust stacks.
2026-03-12478 MW419,000The Socrates South power plant to the right of Buildings 7-12 now has 10 natural gas turbines in place, judging by the number of exhaust stacks. Battery backup has been installed nearby. To the north, a new section of tent buildings has begun east of Buildings 16-20.
2026-05-18478 MW419,000Building 7-11 (Meta tents) look structurally complete but not operational, given there is still construction activity, including at the adjacent Socrates South power plant. Northern tents (Buildings 16-27) are all roofed except for 21 and 27.
2026-08-31612 MW536,000Buildings 7-10 (tents) are operational, based on infrared drone video from RAAD (raad.com) captured on this date. The video suggests that 138.8 MW of nameplate turbine capacity is operating at the Socrates South power plant (about 69% of the 200 MW nameplate capacity), and Buildings 7-10 roof vents are bright on infrared while Buildings 11-12 vents are not. That's 4/6 buildings operating, implying about 67% of capacity, which is consistent with 69% of the power plant operating. In the north, Buildings 16-27 (tents) look to be in a completed state. Each northern set of 6 tents still awaits to be connected to one of the corresponding power plants to become operational. Drone video from August 19th shows no turbines operating at Socrates North, though there are 3 small diesel generators operating. Building 13 (Vantage) is still under construction, we estimate another 3 months before operability.
2026-11-30 (projected)878 MW770,000Socrates South and Socrates North gas power plants are fully operational, enabling the operability of Buildings 11-12 and 16-21. This completes the 2 sets of 6 tents associated with Socrates South and Socrates North. This is based [on](https://dis.puc.state.oh.us/CaseRecord.aspx?CaseNo=25-0188-EL-BGN) [documents](https://dis.puc.state.oh.us/ViewImage.aspx?CMID=A1001001A25E29B42006E01696) [stating](https://www.williams.com/wp-content/uploads/sites/8/2025/03/Socrates-North-Fact-Sheet-Final-1.pdf) "late Third or early Fourth Quarter of 2026", "late 2026", "November 2026", "third quarter of 2026". The timeline also lines up with RAAD drone imagery from 09/08/26 seeing operating turbines at Socrates South and a full set of turbines installed but not yet operating at Socrates North.
2027-01-15 (projected)962 MW843,000Building 13 (Vantage) is operational, based on the pace of construction seen in earlier images.
2027-04-15 (projected)1.0 GW916,000Building 14 (Vantage) is operational, based on it starting construction about 3 months after Building 13.
2027-07-14 (projected)1.1 GW989,000Building 15 (Vantage) operational, based on it starting construction about 3 months after Building 14.
2028-07-01 (projected)1.3 GW1.2 millionBuildings 22-27 (3rd set of 6 Meta tents) are operational. This is a conservative estimate to align with the operability of the [Socrates the Younger](https://drive.google.com/file/d/1Gqu84nBqkyrrwMQy6nSiPykpyQsgLoao/view?usp=sharing) power plant. The power plant is operational by Q3 of 2028 based on the [project schedule](https://drive.google.com/file/d/1QaUa8QxoeLfxm3Dz0y-i0ByrIxgrpEAO/view?usp=sharing). It is announced to produce a maximum of 250MW.

Source: Epoch AI Frontier Data Centers.

Chip deployments

DateChipUnitsBasis
2025-10-14B30034,286Estimate
2026-03-12B300166,015Estimate
2026-08-31B300166,015Estimate
2026-11-30B300166,015Estimate
2027-01-15B300212,285Estimate
2027-04-15B300304,824Estimate
2027-07-14B300333,696Estimate
2028-07-01B300362,568Estimate

Satellite view

Questions

How much power does Meta Prometheus use?

Public data puts the facility power at about 612 MW, with about 1.3 GW planned by 2028. Reported (Epoch AI or owner data).

What chips does Meta Prometheus use?

Reported chips: B300.

Who operates Meta Prometheus?

Meta. Reported users: Meta.

Data centers near New Albany

More Meta data centers

Sources