Meta Hyperion

Meta Hyperion is a data center under construction operated by Meta in Holly Ridge, United States. No power figure is public for this site yet. Likely chips: NVIDIA GPUs (some Meta MTIA) (guess).

Power demand is growing at this site

Key facts

StatusUnder construction
OperatorMeta
UsersMeta
ProjectHyperion
Planned power2.2 GW by 2028-01-01
Epoch AI timeline projection.
AI chipsNVIDIA GPUs (some Meta MTIA)
Guess from the operator, not confirmed. Meta trains on NVIDIA GPUs and adds in-house MTIA chips for inference.
BuildersMortenson
Energy partnersEntergy
AddressHolly Ridge, LA 71269
Coordinates32.46764, -91.62679

Build timeline

DatePowerH100eWhat the satellite images and filings show
2024-12-2000Land clearing begins.
2025-10-1900Foundations are underway for the main buildings, and the overall layout aligns with the [architectural renderings](https://engineering.fb.com/2025/09/29/data-infrastructure/metas-infrastructure-evolution-and-the-advent-of-ai/) published in 2025.
2026-04-1900Building 1 and 2 roof is finished and cooling is at an advanced stage of installation. Building 3 and 6 roof and cooling in progress.
2026-12-01 (projected)00New [power stations](https://drive.google.com/file/d/1D4eUHwEuirNi0g3IU_xGOti3PcC8fcXi/view?usp=sharing) are in service for a 1.8 GW load at Holly Ridge. However, the data center is still not operational.
2028-01-01 (projected)2.2 GW4.1 millionFirst phase is operational, based on a [Meta blog post](https://drive.google.com/file/d/1PmFNgOwkPepwjpGIbNUuPJP0LNgIqe7l/view?usp=sharing). We assume that this aligns with the three natural gas turbines being completed, for a total of 2262 MW capacity, but that these turbines have a backup role. This is close to the 1800 MW of load requested from the grid. Meta [claims](https://engineering.fb.com/2025/09/29/data-infrastructure/metas-infrastructure-evolution-and-the-advent-of-ai/) that "The Hyperion cluster will have a 5-gigawatt capacity once complete", but so far there is no concrete evidence for this happening at the Holly Ridge site alone.

Source: Epoch AI Frontier Data Centers.

Satellite view

Questions

What chips does Meta Hyperion use?

No chips are reported. Based on the operator, the likely chips are NVIDIA GPUs (some Meta MTIA).

Who operates Meta Hyperion?

Meta. Reported users: Meta.

Data centers near Holly Ridge

More Meta data centers

Sources