Coreweave Helios
Coreweave Helios is an operational data center that is still expanding, operated by CoreWeave in Afton, United States. Its power is about 200 MW, growing to about 800 MW by 2029-01. Epoch AI estimates about 160,000 H100-equivalent AI chips (B200).
Power demand is growing at this site
Key facts
| Status | Operational, expanding |
|---|---|
| Operator | CoreWeave |
| Users | OpenAI (speculative) |
| Facility power | 200 MW Reported (Epoch AI or owner data) |
| IT power | 132 MW |
| Planned power | 800 MW by 2029-01-01 Epoch AI timeline projection. |
| AI compute | 160,000 H100-equivalents → 638,000 planned |
| AI chips | B200 Reported (Epoch AI or owner data) |
| GPU capacity if all AI | about 73,000 GPUs If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count. |
| Capital cost | USD 5.0 billion → 20.0 billion planned Epoch AI estimate, 2025 USD. |
| Address | 984 County Road 112, Afton, TX 79220 |
| Coordinates | 33.76286, -100.81680 (city level) |
Build timeline
| Date | Power | H100e | What the satellite images and filings show |
|---|---|---|---|
| 2025-05-31 | 0 | 0 | Land clearing: The former [crypto mining](https://web.archive.org/web/20250423225644/https://investor.galaxy.com/news/news-details/2025/Galaxy-Announces-Commitment-with-CoreWeave-to-Host-Additional-Artificial-Intelligence-and-High-Performance-Computing-Infrastructure-at-Helios-Data-Center-Campus/default.aspx) Helios site begins converting the first building and expanding, with land cleared for additional buildings. |
| 2025-08-27 | 0 | 0 | Backup generator pads and steel framing for chillers are visible, similar to the [3D renderings](https://www.galaxy.com/data-centers). |
| 2026-04-04 | 0 | 0 | Building 1 appears substantially complete. The main white-roofed data hall is visible with exterior mechanical/electrical equipment rows installed on both sides, and adjacent generator/equipment pads plus laydown yards are active. A large graded pad north of Building 1 suggests preparation for the next phase/building. No clear satellite evidence that the AI/HPC facility is operational yet. |
| 2026-06-17 | 0 | 0 | Building 1 appears externally complete and likely Ready for Service, with all cooling/roofing/generators in place, but we're not labeling it operational yet due to visible surrounding yard/construction work. CoreWeave likely still needs time to install chips and use all their designated chip capacity. The pad to the northeast has foundations being laid out for Building 2. |
| 2026-08-30 | 200 MW | 160,000 | Building 1 operational at full capacity. This is based on "Phase I", which is [expected](https://investor.galaxy.com/news/news-details/2025/Galaxy-Announces-Third-Quarter-2025-Financial-Results/default.aspx) to be operational by the end of the first half of 2026. We added two months of overhead to account for remaining construction and/or installation of CoreWeave's chips, since the June 17 image still showed active minor construction around the building. |
| 2028-01-01 (projected) | 600 MW | 479,000 | Building 2 and 3 are operational at full capacity. This corresponds to "Phase II", which is [expected](https://investor.galaxy.com/news/news-details/2025/Galaxy-Announces-Third-Quarter-2025-Financial-Results/default.aspx) to be delivered "throughout 2027". We assume it takes until the end of 2027 to reach full capacity. |
| 2029-01-01 (projected) | 800 MW | 638,000 | Building 4 operational at full capacity. This corresponds to "Phase III", which is [expected](https://investor.galaxy.com/news/news-details/2025/Galaxy-Announces-Third-Quarter-2025-Financial-Results/default.aspx) to be delivered "starting in 2028". We assume it takes until the end of 2028 to reach full capacity. |
Source: Epoch AI Frontier Data Centers.
Chip deployments
| Date | Chip | Units | Basis |
|---|---|---|---|
| 2026-08-30 | B200 | 63,151 | Estimate |
| 2028-01-01 | B200 | 189,452 | Estimate |
| 2029-01-01 | B200 | 252,602 | Estimate |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How much power does Coreweave Helios use?
Public data puts the facility power at about 200 MW, with about 800 MW planned by 2029. Reported (Epoch AI or owner data).
What chips does Coreweave Helios use?
Reported chips: B200.
Who operates Coreweave Helios?
CoreWeave. Reported users: OpenAI.
Data centers near Afton
- Argo Data Center 5.1 km · 53 MW
More CoreWeave data centers
- CoreWeave Ellendale ND United States
- CoreWeave Denton TX United States
- CoreWeave Chester VA United States
- CoreWeave Muskogee OK United States
- CoreWeave Lancaster Greenfield site United States
- CoreWeave Marble NC United States
- CoreWeave Norway Norway
- CoreWeave Dalton 1 & 2 United States
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.