Coreweave Helios

Coreweave Helios is an operational data center that is still expanding, operated by CoreWeave in Afton, United States. Its power is about 200 MW, growing to about 800 MW by 2029-01. Epoch AI estimates about 160,000 H100-equivalent AI chips (B200).

Power demand is growing at this site

Key facts

StatusOperational, expanding
OperatorCoreWeave
UsersOpenAI (speculative)
Facility power200 MW
Reported (Epoch AI or owner data)
IT power132 MW
Planned power800 MW by 2029-01-01
Epoch AI timeline projection.
AI compute160,000 H100-equivalents → 638,000 planned
AI chipsB200
Reported (Epoch AI or owner data)
GPU capacity if all AIabout 73,000 GPUs
If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count.
Capital costUSD 5.0 billion → 20.0 billion planned
Epoch AI estimate, 2025 USD.
Address984 County Road 112, Afton, TX 79220
Coordinates33.76286, -100.81680 (city level)

Build timeline

DatePowerH100eWhat the satellite images and filings show
2025-05-3100Land clearing: The former [crypto mining](https://web.archive.org/web/20250423225644/https://investor.galaxy.com/news/news-details/2025/Galaxy-Announces-Commitment-with-CoreWeave-to-Host-Additional-Artificial-Intelligence-and-High-Performance-Computing-Infrastructure-at-Helios-Data-Center-Campus/default.aspx) Helios site begins converting the first building and expanding, with land cleared for additional buildings.
2025-08-2700Backup generator pads and steel framing for chillers are visible, similar to the [3D renderings](https://www.galaxy.com/data-centers).
2026-04-0400Building 1 appears substantially complete. The main white-roofed data hall is visible with exterior mechanical/electrical equipment rows installed on both sides, and adjacent generator/equipment pads plus laydown yards are active. A large graded pad north of Building 1 suggests preparation for the next phase/building. No clear satellite evidence that the AI/HPC facility is operational yet.
2026-06-1700Building 1 appears externally complete and likely Ready for Service, with all cooling/roofing/generators in place, but we're not labeling it operational yet due to visible surrounding yard/construction work. CoreWeave likely still needs time to install chips and use all their designated chip capacity. The pad to the northeast has foundations being laid out for Building 2.
2026-08-30200 MW160,000Building 1 operational at full capacity. This is based on "Phase I", which is [expected](https://investor.galaxy.com/news/news-details/2025/Galaxy-Announces-Third-Quarter-2025-Financial-Results/default.aspx) to be operational by the end of the first half of 2026. We added two months of overhead to account for remaining construction and/or installation of CoreWeave's chips, since the June 17 image still showed active minor construction around the building.
2028-01-01 (projected)600 MW479,000Building 2 and 3 are operational at full capacity. This corresponds to "Phase II", which is [expected](https://investor.galaxy.com/news/news-details/2025/Galaxy-Announces-Third-Quarter-2025-Financial-Results/default.aspx) to be delivered "throughout 2027". We assume it takes until the end of 2027 to reach full capacity.
2029-01-01 (projected)800 MW638,000Building 4 operational at full capacity. This corresponds to "Phase III", which is [expected](https://investor.galaxy.com/news/news-details/2025/Galaxy-Announces-Third-Quarter-2025-Financial-Results/default.aspx) to be delivered "starting in 2028". We assume it takes until the end of 2028 to reach full capacity.

Source: Epoch AI Frontier Data Centers.

Chip deployments

DateChipUnitsBasis
2026-08-30B20063,151Estimate
2028-01-01B200189,452Estimate
2029-01-01B200252,602Estimate

Satellite view

Questions

How much power does Coreweave Helios use?

Public data puts the facility power at about 200 MW, with about 800 MW planned by 2029. Reported (Epoch AI or owner data).

What chips does Coreweave Helios use?

Reported chips: B200.

Who operates Coreweave Helios?

CoreWeave. Reported users: OpenAI.