CoreWeave data centers
9 CoreWeave data centers in 2 countries.
| Data center | Operator | Location | Status | Power | Chips |
|---|---|---|---|---|---|
| Coreweave Helios | CoreWeave | Afton, United States | Operational, expanding | 200 MW → 800 MW | B200 |
| CoreWeave Ellendale ND | CoreWeave | Ellendale, United States | Operational, expanding | 88 MW → 520 MW | B200 |
| CoreWeave Denton TX | CoreWeave | Denton, United States | Operational, expanding | 367 MW → 395 MW | B200 |
| CoreWeave Chester VA | CoreWeave | VA, United States | Operational, expanding | 114 MW → 197 MW | H100, B200 |
| CoreWeave Muskogee OK | CoreWeave | Muskogee, United States | Under construction | → 181 MW | B300 |
| CoreWeave Lancaster Greenfield site | CoreWeave | PA, United States | Under construction | → 124 MW | NVIDIA GPUs (AMD possible) (guess) |
| CoreWeave Marble NC | CoreWeave | Marble, United States | Operational | 91 MW | B200 |
| CoreWeave Norway | CoreWeave | Vennesla, Norway | Operational | 55 MW | B200 |
| CoreWeave Dalton 1 & 2 | CoreWeave | GA, United States | Operational | 40 MW | B300 |
Get in touch
Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.