CoreWeave Ellendale ND

CoreWeave Ellendale ND is an operational data center that is still expanding, operated by CoreWeave in Ellendale, United States. Its power is about 88 MW, growing to about 520 MW by 2027-06. Epoch AI estimates about 93,000 H100-equivalent AI chips (B200).

Power demand is growing at this site

Key facts

StatusOperational, expanding
OperatorCoreWeave
UsersOpenAI (speculative)
Facility power88 MW
Reported (Epoch AI or owner data)
IT power68 MW
Planned power520 MW by 2027-06-01
Epoch AI timeline projection.
AI compute93,000 H100-equivalents → 505,000 planned
AI chipsB200
Reported (Epoch AI or owner data)
GPU capacity if all AIabout 38,000 GPUs
If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count.
Capital costUSD 2.6 billion → 15.2 billion planned
Epoch AI estimate, 2025 USD.
Address9685 87th Ave SE, Ellendale, ND 58436
Coordinates46.01026, -98.56869

Build timeline

DatePowerH100eWhat the satellite images and filings show
2023-10-3100Start of construction for the first building, according to [Applied Digital](https://ir.applieddigital.com/news-events/press-releases/detail/75/applied-digital-announces-groundbreaking-of). CoreWeave was not leased yet at this site, but this is the construction start date we're using for relevance.
2025-05-2800CoreWeave signed the first lease package for 250 MW. No buildings online yet. This is according to an [SEC 8-k filing](https://www.sec.gov/Archives/edgar/data/1144879/000164117225013199/form8-k.htm) from this date.
2025-08-2900[A new 150 MW lease](https://ir.applieddigital.com/news-events/press-releases/detail/128/applied-digital-finalizes-additional-150mw-lease-with) brings CoreWeave to 400 MW total contracted. The project is now clearly scheduled to be a three-building CoreWeave campus.
2025-10-2765 MW69,000The first 50 MW slice of Building 1 has reached Ready for Service status according to [this report](https://ir.applieddigital.com/news-events/press-releases/detail/133/applied-digital-achieves-ready-for-service-for-phase-1-at). This is the first point where we would count any CoreWeave capacity as operational.
2025-11-2488 MW93,000[This Applied Digital report](https://ir.applieddigital.com/news-events/press-releases/detail/137/applied-digital-completes-phase-ii-ready-for-service-at) says the rest of Building 1 has reached Ready for Service, bringing the first building to its expected 100 MW. We can treat this as the first completed data center building.
2026-03-2788 MW93,000According to satellite imagery, Building 1 looks complete and in service, with the surrounding power/cooling equipment also operational. (Note: this image doesn't provide a view of buildings 2 or 3, though it's very safe to assume they're under construction at this stage, considering they're still under construction in the satellite image 3 months from now.)
2026-06-3088 MW93,000According to satellite imagery, Building 2 is fully roofed and shell complete, with rooftop chillers mostly installed. Building 3 construction is well underway, with about 1/4 of the roofing done and the foundation laid out.
2026-12-31 (projected)114 MW300,000According to the [schedule](https://ir.applieddigital.com/news-events/press-releases/detail/128/applied-digital-finalizes-additional-150mw-lease-with), Building 2 should be online sometime in the second half of 2026. We can estimate the end of 2026 for 250 MW operational.
2027-06-01 (projected)520 MW505,000According to [schedule](https://ir.applieddigital.com/news-events/press-releases/detail/128/applied-digital-finalizes-additional-150mw-lease-with), Building 3 should come online in the first half of 2027. That would bring the full PF1 campus to 400 MW, according to the contract.

Source: Epoch AI Frontier Data Centers.

Chip deployments

DateChipUnitsBasis
2025-10-27B20027,300Estimate
2025-11-24B20036,900Estimate
2026-12-31B200118,700Estimate
2027-06-01B200200,500Estimate

Satellite view

Questions

How much power does CoreWeave Ellendale ND use?

Public data puts the facility power at about 88 MW, with about 520 MW planned by 2027. Reported (Epoch AI or owner data).

What chips does CoreWeave Ellendale ND use?

Reported chips: B200.

Who operates CoreWeave Ellendale ND?

CoreWeave. Reported users: OpenAI.