Data Center Directory

Meta Aiken

Meta Aiken is an operational AI data center operated by Meta in Trenton, United States. Its power is about 168 MW. Epoch AI estimates about 147,000 H100-equivalent AI chips (B300).

Key facts

StatusOperational
OperatorMeta
UsersMeta
Facility power168 MW
Reported (Epoch AI or owner data)
IT power129 MW
AI compute147,000 H100-equivalents
AI chipsB300
Reported (Epoch AI or owner data)
GPU capacity if all AIabout 72,000 GPUs
If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count.
Capital costUSD 4.9 billion
Epoch AI estimate, 2025 USD.
Address7601 State Hwy 105, Trenton, SC 29847, USA
Coordinates33.74166, -81.84234 (city level)

Build timeline

DatePowerH100eWhat the satellite images and filings show
2024-05-3000Land clearing begins
2026-04-0800Buildings 1 and 2 are nearly complete, but there's still some equipment strewn around the site. We expect around 3 more months needed for commissioning and server installation.
2026-08-0790 MW78,000Building 1 is confirmed operational via drone imagery with 8/9 group of coolers with spinning fans. Imagery also confirms all cooling and power infrastructure in place for Building 2.
2026-11-05168 MW147,000Building 2 is operational assuming a 3 month lag compared to Building 1.

Source: Epoch AI Frontier Data Centers.

Chip deployments

DateChipUnitsBasis
2026-08-07B30031,078Estimate
2026-11-05B30058,271Estimate

Satellite view

Questions

How much power does Meta Aiken use?

Public data puts the facility power at about 168 MW. Reported (Epoch AI or owner data).

What chips does Meta Aiken use?

Reported chips: B300.

Who operates Meta Aiken?

Meta. Reported users: Meta.

Data centers near Trenton

More Meta data centers

Sources