Google Storey County is an operational data center that is still expanding, operated by Google in Paradise, United States. Its power is about 214 MW, growing to about 389 MW by 2027-06. Epoch AI estimates about 134,000 H100-equivalent AI chips (TPU v5e, TPU v4, TPU v6e, TPU v5p).
Power demand is growing at this site
Key facts
| Status | Operational, expanding |
|---|---|
| Operator | |
| Users | Google DeepMind (speculative) |
| Facility power | 214 MW Reported (Epoch AI or owner data) |
| IT power | 161 MW |
| Planned power | 389 MW by 2027-06-30 Epoch AI timeline projection. |
| AI compute | 134,000 H100-equivalents → 541,000 planned |
| AI chips | TPU v5e, TPU v4, TPU v6e, TPU v5p Reported (Epoch AI or owner data) |
| GPU capacity if all AI | about 89,000 GPUs If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count. |
| Capital cost | USD 6.1 billion → 11.4 billion planned Epoch AI estimate, 2025 USD. |
| Coordinates | 36.08610, -115.16110 (city level) |
Build timeline
| Date | Power | H100e | What the satellite images and filings show |
|---|---|---|---|
| 2019-03-18 | 0 | 0 | Land clearing begins. |
| 2023-08-30 | 107 MW | 35,000 | Building 1, which was first operational in 2021, has increased power capacity by about 75%. This is based on the expansion of the dry cooling array from 4 to 7 columns (seen on [Google Earth](https://earth.google.com/web/@39.4948785,-119.43174359,1568.8659293a,562.69639351d,35y,-0h,0t,0r/)). Its backup generators also grew from 18 to 33, an 83% increase. Around this time (2023 Q3) the quarterly PUE of the campus is 1.24, down from the initial 1.29 in 2022 Q3. Since no other buildings have been added, these changes indicate an increase in power density, which may entail a new generation of hardware getting installed. |
| 2025-03-11 | 107 MW | 35,000 | Building 2 now has generators in place, but there is still a crane and construction work present. |
| 2025-06-30 | 214 MW | 134,000 | Building 2 is operational. Based on a [Google Earth image](https://earth.google.com/web/@39.49733738,-119.43113543,1552.05877612a,1467.7067385d,35y,0h,0t,0r/) showing complete building shell, mechanical equipment and generators, plus cars parked at the front. |
| 2025-09-28 | 214 MW | 134,000 | Building 3 foundation is underway. Building 2 exterior looks totally clean/landscaped. |
| 2026-04-13 | 214 MW | 134,000 | Building 3 has a partially complete shell, electrical and mechanical equipment. Building 4 foundation is underway. |
| 2027-06-30 (projected) | 389 MW | 541,000 | Building 3 is estimated to be operational. We estimate the operational date by analogy to the time that Building 1 took to go from a foundation to being operational. The power capacity is based on the number of generators reported in an air quality permit [application](https://ndep-onbase.nv.gov/api/Document/AeFo%C3%89pjclbkomJ7CWpPryLOjA6FQT9HFrkSuMWbMXTpKCzSR%C3%81W1f8zzFhGhik1iZCcNSpuTRRqNXD1inrrpBxtA%3D/) (p.92-93). The dry cooler array is more than double the size of the Building 1 array, which suggests an even larger power capacity than we estimate, but we believe the generator-based estimate is more reliable here. |
Source: Epoch AI Frontier Data Centers.
Chip deployments
| Date | Chip | Units | Basis |
|---|---|---|---|
| 2023-08-30 | TPU v5e | 153,165 | Estimate |
| 2023-08-30 | TPU v4 | 34,609 | Estimate |
| 2025-06-30 | TPU v6e | 98,179 | Estimate |
| 2025-06-30 | TPU v5p | 16,521 | Estimate |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How much power does Google Storey County use?
Public data puts the facility power at about 214 MW, with about 389 MW planned by 2027. Reported (Epoch AI or owner data).
What chips does Google Storey County use?
Reported chips: TPU v5e, TPU v4, TPU v6e, TPU v5p.
Who operates Google Storey County?
Google. Reported users: Google DeepMind.
Data centers near Paradise
- Fiberhub LAS1 3.0 km
- DataBank Las Vegas LAS1 3.2 km · 12 MW
- Switch Las Vegas 7 5.3 km · 29 MW
- Switch12 5.4 km · 33 MW
- Switch Las Vegas 12 5.4 km · 5.5 MW
- Switch Edge 1 5.6 km · 2.6 MW
- Switch Las Vegas 16 5.7 km · 6.9 MW
- Switch Las Vegas 8 5.7 km · 26 MW
More Google data centers
- Goodnight United States
- Google Fort Wayne United States
- Google Omaha United States
- Google Columbus United States
- Google Pryor (North) United States
- Google New Albany United States
- Google Lincoln United States
- Google Cedar Rapids United States
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.