Microsoft GPT-4 cluster is an operational AI data center operated by Microsoft in Des Moines, United States. Its power is about 21 MW. Epoch AI estimates about 7,883 H100-equivalent AI chips (NVIDIA A100).
Key facts
| Status | Operational |
|---|---|
| Operator | Microsoft |
| Facility power | 21 MW Reported (Epoch AI or owner data) |
| AI compute | 7,883 H100-equivalents |
| AI chips | NVIDIA A100 Reported (Epoch AI or owner data) |
| Chip count | 25,000 Largest reported cluster at this site (Epoch AI). |
| GPU capacity if all AI | about 9,100 GPUs If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count. |
| Address | Des Moines, Iowa |
| Coordinates | 41.58500, -93.62427 |
GPU clusters at this site
| Cluster | Chips | Count | Power | Since |
|---|---|---|---|---|
| Microsoft GPT-4 cluster | NVIDIA A100 | 25,000 | 21 MW | 2022-04-30 |
Source: Epoch AI GPU Clusters.
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How much power does Microsoft GPT-4 cluster use?
Public data puts the facility power at about 21 MW. Reported (Epoch AI or owner data).
What chips does Microsoft GPT-4 cluster use?
Reported chips: NVIDIA A100.
Who operates Microsoft GPT-4 cluster?
Microsoft.
Data centers near Des Moines
- Connect Des Moines 112 m
- Aureon Downtown 649 m · 2.7 MW
- Data center in Pleasant Hill 8.5 km · 2.3 MW
- Aureon West Des Moines 9.3 km
- Microsoft 9.8 km · 13 MW
- Project Alluvion 10.1 km · 56 MW
- Project Ginger East 11.1 km · 67 MW
- Facebook Altoona Data Center 1 12.7 km · 49 MW
More Microsoft data centers
- Microsoft Fairwater Wisconsin United States
- Crusoe Abilene Expansion United States
- Microsoft Fairwater Atlanta United States
- Microsoft Goodyear United States
- Microsoft Boydton Data Center United States
- Microsoft Project Osmium United States
- OpenAI/Microsoft Goodyear Arizona United States
- Microsoft CYS Datacenter United States
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.