QTS Richmond 2

QTS Richmond 2 is an operational AI data center in Sandston, United States. Its power is about 252 MW. Epoch AI estimates about 183,000 H100-equivalent AI chips.

Key facts

StatusOperational
Facility power252 MW
Reported (Epoch AI or owner data)
IT power180 MW
AI compute183,000 H100-equivalents
GPU capacity if all AIabout 100,000 GPUs
If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count.
Capital costUSD 6.8 billion
Epoch AI estimate, 2025 USD.
Energy partnersDominion Energy
Address6030–6070 Technology Blvd, Sandston, VA 23150
Coordinates37.52348, -77.31581 (city level)

Build timeline

DatePowerH100eWhat the satellite images and filings show
2022-04-0100Land clearing begins.
2024-01-2900Building 1 and 2 look complete but we don't think they are operational, as the substation is still under construction.
2024-06-2300Still not many cars parked at Building 1 and 2, and the east substation looks very close to completion, based on a [Google Earth image](https://earth.google.com/web/@37.48655608,-77.24244153,55.96289131a,2859.52501034d,30.00094375y,0h,0.5917603t,0r/data=ChYqEAgBEgoyMDI0LTA2LTIzGAFCAggBMikKJwolCiExWVNYSWZQZkcydXVMYm1nUDkyc2NObE1QenF1VGRVV2cgAToDCgEwQgIIAEoICMOJgf0CEAE).
2025-02-04101 MW52,000Building 1 and 2 are operational, based on the east substation looking complete and the carparks being more full. Building 3 has cooling and generators mostly installed. Building 4 roof is partly completed.
2025-11-19101 MW52,000The west substation looks complete, based on a [Google Earth image](https://earth.google.com/web/@37.48673632,-77.24119214,61.15398527a,3616.77426559d,30.00094375y,0.00000001h,0.59183057t,0r/data=CgwqBggBEgAYAUICCAEyKQonCiUKITFZU1hJZlBmRzJ1dUxibWdQOTJzY05sTVB6cXVUZFVXZyABOgMKATBCAggASggIw4mB_QIQAQ). This image also shows one corner of Building 5 that still has construction work, so it's probably not operational.
2025-12-31202 MW139,000Building 3 and 4 are operational, based on the substation being completed earlier, the buildings looking complete, and carparks being moderately full. Building 5 still has construction work.
2026-02-13202 MW139,000Building 5 still has construction work at the perimeter, but given how close it looks to completion, we estimate it's only about 3 months away from operational.
2026-05-14252 MW183,000Building 5 is estimated to be operational, based on the previous entry.

Source: Epoch AI Frontier Data Centers.

Satellite view

Questions

How much power does QTS Richmond 2 use?

Public data puts the facility power at about 252 MW. Reported (Epoch AI or owner data).