Anthropic-Amazon New Carlisle

Anthropic-Amazon New Carlisle is an operational data center that is still expanding, operated by Amazon Web Services in New Carlisle, United States. Its power is about 1.2 GW, growing to about 2.3 GW by 2028-03. Epoch AI estimates about 818,000 H100-equivalent AI chips (Trainium2).

Power demand is growing at this site

Key facts

StatusOperational, expanding
OperatorAmazon Web Services
UsersAnthropic
ProjectProject Rainier
Facility power1.2 GW
Reported (Epoch AI or owner data)
IT power1.0 GW
Planned power2.3 GW by 2028-03-17
Epoch AI timeline projection.
AI compute818,000 H100-equivalents → 1.7 million planned
AI chipsTrainium2
Reported (Epoch AI or owner data)
GPU capacity if all AIabout 580,000 GPUs
If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count.
Capital costUSD 39.3 billion → 72.9 billion planned
Epoch AI estimate, 2025 USD.
Water use21.00 million gallons per day
Address55001 Larrison Blvd, New Carlisle, IN 46552
Coordinates41.70569, -86.50982 (city level)

Build timeline

DatePowerH100eWhat the satellite images and filings show
2024-02-0900Land clearing begins in the northern section
2024-06-1000Land clearing begins in the southern section
2025-05-1000Roof complete on building 11
2025-06-23478 MW300,000Buildings 1-7 are operational. Based on all of the roofs being completed for over 5 months.
2025-09-26478 MW300,000Roof complete on building 16. Generators are being installed for buildings 8-15. In the north, Building 17 and 18 are under construction. To the south of buildings 8-16, a concrete pad is visible, and an expanded car park next to it.
2025-10-17478 MW300,000Confirmation that nearly 500,000 chips are operational, which fits buildings 1-7. In an [interview](https://www.youtube.com/watch?v=jwgW_gHI1Vs&t=220s), AWS CEO says "they're already running...about 500,000 [Trainium2] chips in Indiana today".
2025-12-23751 MW471,000Buildings 8-11 are operational, given it's been over 7 months since their roofs were complete, and the backup generators and roof chimneys look complete. The roof is almost complete for Building 17 and 18.
2026-02-09751 MW471,000Buildings 12-16 still have a few generators that look incomplete, so they are unlikely to be operational just yet. Buildings 17-18 still have ongoing roof work, no generators. Just south of Buildings 9-16, the outlines of a site for Buildings 19-32 are taking shape.
2026-03-231.1 GW686,000Buildings 12-16 are operational. Based on how long previous buildings took, when they were in a similar state to Buildings 12-16 in December.
2026-06-031.1 GW686,000Buildings 17-18 fully roofed but still having surrounding generators/cooling under construction. Cleared land for buildings 19-32 is still bare, with no building foundations visible yet. Based on satellite imagery.
2026-10-191.2 GW818,000Buildings 17-18 are operational. This is an estimate based on a rule of thumb of "operational 5 months after roof is complete", assuming the roofs took one more month after 2025-12-23. Also added four more months to account for commissioning and adjacent cooling units not being complete yet.
2028-03-17 (projected)2.3 GW1.7 millionBuildings 19-32 are operational. This is an estimate based on how long Buildings 1-16 took to become operational. In May 2026, the foundation of several buildings and a substation was visible at the site of Buildings 19-32. Buildings 1-16 took 1 year and 10 months to go from a similar state to operational. So we add 1 year and 10 months to May 2026 to get this date estimate. The power capacity is based on an [air quality permit](https://t.co/HsAO7oyKa2) filed in May 2026, and the compute capacity is based on Trainium3 chips.

Source: Epoch AI Frontier Data Centers.

Chip deployments

DateChipUnitsBasis
2025-06-23Trainium2457,200Reported
2025-12-23Trainium2718,400Estimate
2026-03-23Trainium21,044,980Estimate
2026-10-19Trainium21,044,980Estimate

Satellite view

Questions

How much power does Anthropic-Amazon New Carlisle use?

Public data puts the facility power at about 1.2 GW, with about 2.3 GW planned by 2028. Reported (Epoch AI or owner data).

What chips does Anthropic-Amazon New Carlisle use?

Reported chips: Trainium2.

Who operates Anthropic-Amazon New Carlisle?

Amazon Web Services. Reported users: Anthropic.

Data centers near New Carlisle

More Amazon Web Services data centers

Sources