YTL Johor

YTL Johor is an operational data center that is still expanding, in Johor, Malaysia. Its power is about 155 MW, growing to about 389 MW by 2028-08. Epoch AI estimates about 154,000 H100-equivalent AI chips (B200, B300).

Power demand is growing at this site

Key facts

StatusOperational, expanding
Facility power155 MW
Reported (Epoch AI or owner data)
IT power113 MW
Planned power389 MW by 2028-08-01
Epoch AI timeline projection.
AI compute154,000 H100-equivalents → 585,000 planned
AI chipsB200, B300
Reported (Epoch AI or owner data)
GPU capacity if all AIabout 63,000 GPUs
If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count.
Capital costUSD 4.3 billion → 10.8 billion planned
Epoch AI estimate, 2025 USD.
AddressYTL Green Data Centers, Kulai, Johor, Malaysia
Coordinates1.66667, 103.60000 (city level)

Build timeline

DatePowerH100eWhat the satellite images and filings show
2023-11-0100Land clearing begins for Building 1.
2025-11-0326 MW24,000Building 1 is operational with Nvidia GB200s, according to the [local investment development authority](https://www.midf.com.my/sites/corporate/files/2025-11/ytl_power-cu-all_systems_go_for_ai_dc-mbsbr-031125.pdf).
2026-03-14138 MW138,000Building 2 is operational, assuming 3 months to structural completion plus 3 months fit-out after this [video](https://youtu.be/HODHjDbFt10?si=749v3V9LD4gkTDE2&t=212). Solar panels are also being installed to the north west of the campus.
2026-05-15155 MW154,000Building 1 added 4 two-fan cooling towers (config 3), installed mid May of 2026. This capacity is not reflected in any disclosure (the building is still reported at 20MW IT load).
2026-07-13155 MW154,000Satellite imagery confirms Buildings 1 and 2 are structurally complete. Buildings 3 and 4 are underway, and construction equipment can be seen on the plot for Building 5. Extensive solar panel arrays have been built out.
2028-08-01 (projected)389 MW585,000Estimate: all five AI buildings operational. The mean time from first ground activity to operational across buildings 1 and 2 was 25.6 (25.1 and 26.0 months). Buildings 3 and 4 have been underway since Mar 2026, and building 5's plot only has construction equipment as of Jul 2026, so +25 months gives Aug 2028 as campus completion. Company guidance is faster: capacity "expected to double to 600MW by the end of 2027" per [Kenanga via The Star](https://www.thestar.com.my/business/business-news/2026/06/24/dc-expansion-to-lift-ytl-power); JDC4 phases Sep-25/Sep-26/Sep-27 per [MIDF](https://www.midf.com.my/sites/corporate/files/2025-11/ytl_power-cu-all_systems_go_for_ai_dc-mbsbr-031125.pdf). The resulting ~429MW IT independently matches Kenanga's "expected IT load of 430MW" for the 600MW park ([Kenanga, 9 Dec 2024](https://www.kenanga.com.my/wp-content/uploads/2024/12/YTLPOWR-241209-CU-Kenanga.pdf)).

Source: Epoch AI Frontier Data Centers.

Chip deployments

DateChipUnitsBasis
2025-11-03B2009,576Estimate
2026-03-14B30045,144Estimate
2026-05-15B30051,192Estimate

Satellite view

Questions

How much power does YTL Johor use?

Public data puts the facility power at about 155 MW, with about 389 MW planned by 2028. Reported (Epoch AI or owner data).

What chips does YTL Johor use?

Reported chips: B200, B300.