Bridge Data Centres MY06

Bridge Data Centres MY06 is an operational AI data center operated by ByteDance in Johor, Malaysia. Its power is about 315 MW. Epoch AI estimates about 221,000 H100-equivalent AI chips (A100, H100, B200).

Key facts

StatusOperational
OperatorByteDance
UsersByteDance (likely)
Facility power315 MW
Reported (Epoch AI or owner data)
IT power243 MW
AI compute221,000 H100-equivalents
AI chipsA100, H100, B200
Reported (Epoch AI or owner data)
GPU capacity if all AIabout 140,000 GPUs
If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count.
Capital costUSD 9.2 billion
Epoch AI estimate, 2025 USD.
AddressBridge Data Centres, Sedenak Tech Park, Johor, Malaysia
Coordinates1.71266, 103.52573 (city level)

Build timeline

DatePowerH100eWhat the satellite images and filings show
2021-10-0100Land clearing begins for campus 1, seen via satellite imagery. This start date is corroborated by the [Malaysian Investment Development Authority](https://www.mida.gov.my/media-release/bridge-data-centres-and-bytedance-celebrate-grand-opening-of-the-first-phase-hyperscale-data-centre-my06-in-johor-malaysia/), citing November for officially first breaking ground.
2022-12-3125 MW6,468Building 1 (MY06-1) is operational. The [SEC filing for Chindata](https://www.sec.gov/Archives/edgar/data/1807192/000095017022025569/cd-ex99_1.htm) and [local news sources](https://www.malaymail.com/news/money/2022/10/21/mida-malaysia-still-most-desirable-location-for-data-centre-hubs-in-the-region/34929) reported the building was in service as of October 20, but only a [subsequent filing](https://www.sec.gov/Archives/edgar/data/1807192/000095017023015950/cd-20221231.htm) confirmed 19 MW was utilized by December 31, so we conservatively assume December 31.
2023-03-0125 MW6,468[Drone footage](https://www.youtube.com/watch?v=ozi5G1Lt4Ew) indicates that Building 1 is operating at full capacity, with 4 of 5 cooling tower fans spinning. Building 2 has 2 of 21 fans spinning and some ongoing construction work, so we assume it's not fully operational yet. We estimate another 3 months until full utilization.
2023-05-3079 MW21,000Building 2 (MY06-2) is operational.
2024-11-05148 MW65,000Building 3 and 4 are operational. Building 3 was [originally scheduled](https://www.sec.gov/Archives/edgar/data/1807192/000119312523034103/d282677dex994.htm) for 2024Q4, and seemed partly operational in June, so it's likely to be fully utilized by this date. Building 4 was [scheduled](https://www.sec.gov/Archives/edgar/data/1807192/000095017023045611/cd-ex99_1.htm) for delivery starting 2024Q1, but it typically takes a few more months to fit out and reach full utilization, so we think it's only fully utilized by this date. At Campus 2, Buildings 5-7 and Building 9 are close to finishing construction while Buildings 8 and 10 shells are still under construction. The Campus 2 substation looks complete.
2025-02-09148 MW65,000Construction looks complete on Building 5, 6 and 7, but we allow 3 more months for fit-out and ramping before declaring them operational.
2025-05-25315 MW221,000Buildings 5-7 are operational.
2025-09-23315 MW221,000Buildings 8 and 9 look structurally complete. The remaining building, building 10, still has construction material around it and scaffolding on the roof, with cooling units yet to be installed.
2026-03-03315 MW221,000All cooling units are now installed on Building 10. [Drone footage](https://www.youtube.com/watch?v=BVdGV8FFaLw) from the same month shows most cooling units operating for Buildings 5-7, but none (or very few) for Buildings 8-10. So we don't think Buildings 8-10 are operating significantly yet.
2026-09-13315 MW221,000No visible construction work on Buildings 8-10, but no cars in their carparks either (whereas Building 7 has many cars). So we still don't think Buildings 8-10 are utilized.

Source: Epoch AI Frontier Data Centers.

Chip deployments

DateChipUnitsBasis
2022-12-31A10020,513Estimate
2023-05-30A10065,857Estimate
2024-11-05H10044,720Estimate
2025-05-25B20061,573Estimate

Satellite view

Questions

How much power does Bridge Data Centres MY06 use?

Public data puts the facility power at about 315 MW. Reported (Epoch AI or owner data).

What chips does Bridge Data Centres MY06 use?

Reported chips: A100, H100, B200.

Who operates Bridge Data Centres MY06?

ByteDance. Reported users: ByteDance.