Data Center Directory

OpenAI Stargate Shackelford

OpenAI Stargate Shackelford is a data center under construction operated by Oracle in Shackelford County, United States. No power figure is public for this site yet. Likely chips: NVIDIA GPUs (some AMD Instinct) (guess).

Power demand is growing at this site

Key facts

StatusUnder construction
OperatorOracle
UsersOpenAI
ProjectStargate
Planned power2.0 GW by 2028-11-11
Epoch AI timeline projection.
AI chipsNVIDIA GPUs (some AMD Instinct)
Guess from the operator, not confirmed. Oracle Cloud sells NVIDIA and AMD GPU capacity.
InvestorsOracle, OpenAI
Address175 Private Road 1604, Abilene, TX 79601, Shackelford County
Coordinates32.59656, -99.50209 (city level)

Build timeline

DatePowerH100eWhat the satellite images and filings show
2025-08-0100Land clearing begins.
2026-01-1800The layout of Buildings 1-5 is visible. Steel framing has just started on Building 1.
2026-04-1400Steel framing is underway for Buildings 1-3, and roofing is underway for Building 1.
2026-09-0400Buildings 1-5 shells complete and fully roofed. Buildings 1-3 appear to be actively installing cooling and backup generators nearby. The pads for Buildings 6-10 to the north have also been visibly cleared, with foundations for Buildings 6 and 7 underway.
2027-08-15 (projected)196 MW355,000Building 1 is operational (estimate). TDLR lists the construction completion date for Building 1 as 2027-02-15. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.
2027-10-19 (projected)392 MW712,000Building 2 is operational (estimate). TDLR lists the construction completion date for Building 2 as 2027-04-19. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.
2027-11-18 (projected)588 MW1.1 millionBuilding 3 is operational (estimate). TDLR lists the construction completion date for Building 3 as 2027-05-18. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.
2028-02-11 (projected)784 MW1.4 millionBuilding 4 is operational (estimate). TDLR lists the construction completion date for Building 4 as 2027-08-11. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.
2028-03-08 (projected)980 MW1.8 millionBuilding 5 is operational (estimate). TDLR lists the construction completion date for Building 5 as 2027-09-08. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.
2028-04-04 (projected)1.2 GW2.3 millionBuilding 6 is operational (estimate). TDLR lists the construction completion date for Building 6 as 2027-10-04. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.
2028-05-12 (projected)1.4 GW2.9 millionBuilding 7 is operational (estimate). TDLR lists the construction completion date for Building 7 as 2027-11-12. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.
2028-10-17 (projected)1.6 GW3.5 millionBuilding 8 is operational (estimate). TDLR lists the construction completion date for Building 8 as 2028-04-17. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.
2028-10-18 (projected)1.8 GW4.0 millionBuilding 9 is operational (estimate). TDLR lists the construction completion date for Building 9 as 2028-04-18. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.
2028-11-11 (projected)2.0 GW4.6 millionBuilding 10 is operational (estimate). TDLR lists the construction completion date for Building 10 as 2028-05-11. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.

Source: Epoch AI Frontier Data Centers.

Satellite view

Questions

What chips does OpenAI Stargate Shackelford use?

No chips are reported. Based on the operator, the likely chips are NVIDIA GPUs (some AMD Instinct).

Who operates OpenAI Stargate Shackelford?

Oracle. Reported users: OpenAI.

Data centers near Shackelford County

More Oracle data centers

Sources

Correct this page or get the data

Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.