Aligned Data Centers
Aligned Data Centers is an operational data center operated by Aligned Data Centers in Lithia Springs, United States. Our footprint estimate of its power is about 50 MW.
Key facts
| Status | Operational |
|---|---|
| Operator | Aligned Data Centers |
| Facility power | 50 MW (range 25 MW to 80 MW) Estimate from building footprint, low confidence. Footprint estimate: about 41,559 m² building outline x 1 floor(s) x 1.2 kW/m². |
| GPU capacity if all AI | about 21,000 GPUs If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count. |
| Address | North River Road 1551, 30122, Lithia Springs |
| Coordinates | 33.72596, -84.61957 |
| Website | aligneddc.com/atlanta-data-centers |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How much power does Aligned Data Centers use?
We estimate the facility power at about 50 MW. Estimate from building footprint, low confidence.
Who operates Aligned Data Centers?
Aligned Data Centers.
Data centers near Lithia Springs
- Douglasville 564 m · 68 MW
- Flexential - Atlanta/Douglasville (ATL5) 680 m · 54 MW
- Douglasville 2 934 m · 65 MW
- DC BLOX data center in Lithia Springs 995 m · 32 MW
- Amazon Web Services data center in Lithia Springs 2.3 km · 51 MW
- Atlanta, GA 2.8 km · 9.5 MW
- Microsoft 3.3 km · 3.9 MW
- Westlake Data Center 3.8 km · 14 MW
More Aligned Data Centers data centers
- Aligned Ashburn (IAD-02) United States
- Aligned Phoenix (PHX-01) United States
- Aligned Data Centers DFW-04 United States
- Alinged Data Center DFW-03 United States
- Aligned DC - PDX-01 United States
- Aligned Data Centers United States
- Aligned Dallas (DFW-01) United States
- Aligned Ashburn (IAD-01) United States
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.