Key facts
| Status | Operational |
|---|---|
| Operator | nLighten HQ |
| Facility power | 8 MW (range 4 MW to 13 MW) Estimate from building footprint, low confidence. Footprint estimate: about 6,629 m² building outline x 1 floor(s) x 1.2 kW/m². |
| GPU capacity if all AI | about 3,400 GPUs If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count. |
| Networks | 2 networks PeeringDB. |
| Also known as | nLighten Swindon |
| Address | 11c Broadmoor Rd |
| Coordinates | 51.60213, -1.72937 |
| Website | nlighten.com/en/united-kingdom-data-centers/swindon |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How much power does nLighten Swindon BRS2 use?
We estimate the facility power at about 8 MW. Estimate from building footprint, low confidence.
Who operates nLighten Swindon BRS2?
nLighten HQ.
Data centers near Swindon
- Nationwide Building Society data center in Swindon 8.1 km · 4 MW
- AWS Swindon Data Centre 9.0 km · 14 MW
- Vodafone 9.9 km · 8.5 MW
- R89 28.8 km · 2.1 MW
- Amazon Web Services data center in Didcot 32.3 km · 6.1 MW
- Gigastream Oxford 1 35.8 km
- Amatis Newbury 36.3 km
- Stream Networks - Newbury 36.4 km
More nLighten HQ data centers
- nLighten Leeds LBA1 United Kingdom
- nLighten Strasbourg SXB1 France
- nLighten Besancon MLH1 France
- nLighten Liverpool LPL1 United Kingdom
- nLighten Paris PAR2 France
- nLighten Sophia Antipolis NCE1 France
- nLighten Paris PAR1 France
- nLighten Paris PAR3 France
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.