Colt London West
Colt London West is an operational data center operated by Colt in London, United Kingdom. Our footprint estimate of its power is about 6 MW.
Key facts
| Status | Operational |
|---|---|
| Operator | Colt |
| Facility power | 6 MW (range 3 MW to 9.7 MW) Estimate from building footprint, low confidence. Footprint estimate: about 5,038 m² building outline x 1 floor(s) x 1.2 kW/m². |
| GPU capacity if all AI | about 2,600 GPUs If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count. |
| Address | Volt Avenue, NW10 6PW, London |
| Coordinates | 51.53194, -0.25761 |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How much power does Colt London West use?
We estimate the facility power at about 6 MW. Estimate from building footprint, low confidence.
Who operates Colt London West?
Colt.
Data centers near London
- Equinix LD9 - London, Powergate 155 m · 16 MW
- Vantage LHR2 161 m · 5.2 MW
- Data center in Harlesden 372 m · 23 MW
- Options IT - Park Royal Datacenter (PRDC) 387 m · 1.2 MW
- Vantage Data Centers LHR1 504 m · 9.3 MW
- Data center in Acton 1.2 km · 6.2 MW
- Equinix LD3 - London, Park Royal 1.4 km · 4.1 MW
- Redwire 4.2 km
More Colt data centers
- Colt Data Center India
- Colt Paris 3 France
- Datacenter Colt France
- Colt FRA3 Germany
- colt data center in Islington United Kingdom
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.