Anthropic Barber Lake
Anthropic Barber Lake is a data center under construction operated by Cipher Mining in Snyder, United States. No power figure is public for this site yet. Likely chips: TPU v7.
Power demand is growing at this site
Key facts
| Status | Under construction |
|---|---|
| Operator | Cipher Mining |
| Users | Anthropic |
| Planned power | 300 MW by 2027-04-30 Epoch AI timeline projection. |
| AI chips | TPU v7 Reported (Epoch AI or owner data) |
| Coordinates | 32.39303, -100.86351 (city level) |
Build timeline
| Date | Power | H100e | What the satellite images and filings show |
|---|---|---|---|
| 2025-09-18 | 0 | 0 | Site grading and civil works begin. |
| 2025-11-29 | 0 | 0 | Foundations of Building 1 are visible. |
| 2026-07-30 | 0 | 0 | Building 1 shell is complete, with rooftop units installed, and most air-cooled chillers in place in a ground yard to the north. Most of the 120 backup diesel generators are also in place. Substantial progress since Nov 2025, still under construction and not yet energized. |
| 2026-12-30 (projected) | 244 MW | 234,000 | Building 1 Phase I is operational: 168 MW critical IT power (244 MW gross), running Google TPU v7 (chip type inferred, tagged likely). We estimate ~Dec 2026, about 3 months later than the disclosed target, because the site is shell-complete but not yet energized as of the Jul 2026 image. Disclosed target: [Cipher 2025-09-25 PR](https://www.globenewswire.com/news-release/2025/09/25/3156107/0/en/Cipher-Mining-Signs-168-MW-10-Year-AI-Hosting-Agreement-with-Fluidstack.html) states the 168 MW critical IT load is "expected to be delivered by September 2026." |
| 2027-04-30 (projected) | 300 MW | 289,000 | Building 1 Phase II is operational: 207 MW total critical IT (300 MW gross). Phase II adds 39 MW critical IT (see [Cipher 2025-11-20 PR](https://www.globenewswire.com/news-release/2025/11/20/3191801/0/en/Cipher-Mining-Signs-Additional-56-MW-10-Year-AI-Hosting-Agreement-with-Fluidstack.html)). We estimate ~Apr 2027, about 3 months later than the ~Q1 2027 target, based on construction progress. |
Source: Epoch AI Frontier Data Centers.
Chip deployments
| Date | Chip | Units | Basis |
|---|---|---|---|
| 2026-12-30 | TPU v7 | 100,478 | Estimate |
| 2027-04-30 | TPU v7 | 123,804 | Estimate |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
What chips does Anthropic Barber Lake use?
Reported chips: TPU v7.
Who operates Anthropic Barber Lake?
Cipher Mining. Reported users: Anthropic.
Sources
- Epoch AI, Frontier Data Centers
- Cipher signs 168 MW AI hosting deal with Fluidstack, Google backs it (Sep 2025)
- Cipher adds 56 MW gross to reach 300 MW at Barber Lake (Nov 2025)
- Cipher 8-K exhibit: 207 MW total critical IT load (SEC, Nov 2025)
- Anthropic to expand use of Google Cloud TPUs (Oct 2025)
- Anthropic $50B US AI infrastructure with Fluidstack (Nov 2025)
- DCD: Cipher secures Fluidstack as customer, Google as investor
- Air quality permit listing 60 x 3 MW plus 60 x 3.1MW backup generators
Correct this page or get the data